Dolna Odra Power Plant in Nowy Czarnów - 2021/2022

Construction of new gas and steam units with a total capacity of 1.4 thousand MW at Dolna Odra Power Plant in Nowy Czarnów is an investment of strategic importanceThis power plant will be the most modern in Europe, the most modern turbines with the highest efficiency available on the market will be installed hereIt will emit 1/3 CO2 of what other power plants in the Polish Electricity Grid emit on average

Scope of work of NIZBUD Sp. z o. o.: carpentry, concrete and reinforcement works with the provision of auxiliary materials

Construction of industrial foundations for technological devices.

Implementation time: 06/2021 - 06/2022

Ordering party: POLIMEX Budownictwo Sp. z o. o. Sp.k.